What does the VA approval cost?

Below is a list of the costs involved in having your construction product VA approved or your VA approval renewed. The prices vary according to duration.

When you apply for a VA approval, the basis will be the existing standards for water supply and drainage systems. This means that the approval process comprises equipment which is a part of a water distribution or drainage system in buildings with an associated piece of land.

We decide whether the construction product can be approved on the basis of the information available about the product, such as reports from foreign testing institutions. We may also choose to have the product tested at a testing institute acknowledged by us. The test results will be taken into consideration as part of the overall assessment of how well suited the product is to obtain a VA approval.

The approval process also includes an examination of whether water supply and drainage systems are completed and designed in a manner providing sufficient security with regard to fire, safety and health aspects. The product must also be of satisfactory quality when used.

You can apply for approval of your product for one specific use.

Price of VA approval as on 1 January 2020

Class

Duration of approval

 

5 years

4 years

3 years

2 years

1 year

1

4,500

3,600

2,700

2,700

2,700

2

7,200

5,800

4,300

3,450

2,700

3

11,650

9,200

7,000

5,250

4,300

4

17,450

13,950

10,550

7,900

6,100

5

26,050

20,850

15,650

12,150

9,500

Price in Euro (exchange rate 7.40)

Class

Duration of approval

 

5 years

4 years

3 years

2 years

1 year

1

608

486

365

365

365

2

973

784

581

466

365

3

1,574

1,243

946

709

581

4

2,358

1,885

1,426

1,068

841

5

3,520

2,818

2,115

1,642

1,284

 

Prices are adjusted in relation to the net price index for 2015 and rounded off to the nearest DKK 50.

A renewal for three years is regarded as an approval for three years.

The price of renewal implies that new approvals are issued in case of changes, for instance if an approval is extended, transferred or discontinued.

If you have changed your construction product in relation to an existing VA approval, you will have to pay the renewal price, however, not more than DKK 3,000. It is a precondition that the changes are not essential to the contents and extent of the construction product. The new approval is issued to you with the same expiry date as that of the original approval.

Kontakt

Peter Fritzel
Peter Fritzel Projektleder | Project Manager
ETA
E: pf@etadanmark.dk
T: 72245966
Martin Frantzen
Martin Frantzen Projektleder | Project Manager
ETA
E: mfr@etadanmark.dk
T: 72245975